Fertiliser Plant Shutdown Works
MARKET INDUSTRIAL
SECTOR CHEMICAL
Origin(s)
Nansha, China Hazira, India Scanzorosciate, Italy
Destination
Burrup Peninsula, Australia

Project

Fertiliser Plant Shutdown Works
Equipment
Process Vessels
Total Volume
1,800 cbm
Total Weight
1,900 mt
Heaviest Lift
130 mt
Year
2018
PROJECT OVERVIEW

Westlink was engaged to provide multimodal logistics solutions for several process vessels including two pressure vessels and a desalination system, all stemming from various fabrication origins from around the world. These vessels were delivered and installed as major shutdown works for a fertiliser plant located at the Burrup Peninsula in Australia.

SCOPE
  • Heavy Lift Vessels (HLVs) – Port of Origin(s) to Dampier
  • Roll-On-Roll-Off Vessel (RoRo) – Port of Origin to Fremantle
  • Craneage – at various locations at ports and at delivery points at site
  • Heavy Haulage – Port of Discharge to Burrup Peninsula fertiliser plant

HIGHLIGHTS
  • Zero LTIs
  • Heavy lift and haulage for 130 metric ton (mt)
  • Oversize transport envelope – 20 x 9 x 6 metres
  • Met all tight installation windows for delivery
  • Heavy haulage through to congested site installation points
  • No disruption to fertiliser production