Project
Westlink managed the turnkey end-to-end logistics of fifty-nine (59) oversize process tanks from a local fabrication yard to the Covalent Lithium Refinery project site in Kwinana.
-
Pre-shipment inspections at fabrication yard
-
Craneage – loading trailers with tanks at fabrication yard
-
Oversized Haulage – fabrication yard to Kwinana project site
-
Oversized Traffic Management – escorts, wardens and overhead powerline management
-
Construction Coordination – coordination with site team to unload trailers into laydown or direct installation
-
Zero LTIs
-
No missed warden / escort dates
-
Laydown management with delivery coordination to site according to construction schedule
-
Various bespoke trailer layout and lashing designs due to individual design of each tank
-
Safe and seamless traffic management through busy built up industrial / urban area of Kwinana